Two projects totaling 2,215 apartments across four towers were approved by the Jersey City Redevelopment Agency board of commissioners last night. The land deal and accompanying redevelopment will help “stabilize the finances” of Jersey City’s last hospital (Jersey City Medical Center), fund an expansion of JCMC’s emergency department, and likely put over $50 million in the city’s coffers. The two projects are now rolled under a single redevelopment agreement with the same developer, but they were once distinct projects with very different histories.

A Deal to Support the JCMC
One of the projects, involving 1,700 apartments across three high-rise towers, had been opposed by then-Councilman Solomon when the city council voted on it last September. Solomon claimed municipal land sales were “unsustainable” budget gimmicks and lamented the project did not have any below-market-rate apartments. The service workers union SEIU Local 32BJ also objected at the time, demanding concessions to the union [Hudson County View].
After he won the mayoral election in December of 2025, the 1,700-unit project was withdrawn from the agenda at the December JCRA meeting, along with several other projects that were asking for redeveloper designation.
According to sources, the Solomon administration, whose appointees now control the JCRA board of commissioners, was trying to withhold redeveloper designation on several of these projects and demanding unfunded givebacks. Large givebacks, including inclusion of more income-restricted apartments, would almost certainly have resulted in less funding for JCMC and the city’s budget gap, due to reduced land values. However, the project approved by the JCRA last night was essentially unchanged from the version presented at a February 18, 2025 board meeting [Feb 2025 JCRA Presentation].
In September 2025, the project was slated to add $26.75 million to the municipal ledger line. The most notable difference was a confirmation by the project’s attorney, W. Nevins McCann, that the developers (a joint venture of KRE and Related Group) had committed to a labor peace agreement with Local 32BJ.

The massing of the towers was rearranged somewhat, with skinnier and taller towers than the 2025 version. In the new version, the towers are 38, 44, and 52 stories (compared to 34, 34, and 49 stories in a previous version). A structured parking podium would also be included, replacing the surface parking spots that now occupy the land.
The land is owned by JCMC, and they will also receive almost $30 million from the land sale, which they will place toward expanding JCMC’s emergency-room facilities and bolstering the hospital’s finances, as noted in 2025.
The attorneys for the developers had also previously noted they will build out all utilities, roads, and infrastructure on the site, which will help improve storm-water detention and sewer overflow in downtown Jersey City. In addition to housing, new space for ground-floor retail will be added. Other public amenities will include a new one-acre public park to be maintained by the building’s owners and an expansion of the Morris Canal Greenway.

This project would sit on what are known as Blocks 7 and 8 of the Grand/Jersey Redevelopment Plan, land that is wedged north of the light rail tracks, south of JCMC’s hospital buildings, and west of Jersey Avenue.

Reviving a Second Redevelopment Site
The second development site under consideration is a 515-unit, 44-story tower at 185 Monmouth Street, also known as Block 5/6 of the Grand/Jersey Redevelopment Plan, just west of Blocks 7 and 8. This site has a long and troubled history. The JCRA had first tried to sell the site in February 2017 to Argent Ventures under the address 52 Aetna Street [JCRA], but the sale fell through and an agreement was never executed. At its January 2024 meeting, the agency designated a new redeveloper who agreed to buy the land for $29 million and build a 515-unit project [NJ Biz]. However, by October the deal was off, with the city unilaterally claiming that the developer was in default and terminating the sale and redevelopment agreement [JCRA].
The latest iteration retains 515 units, but the developer is now the KRE-Related joint venture. Under the plan presented yesterday evening, 10% of the apartments are designated as workforce housing (restricted to households earning up to 120% of Area Median Income) whereas the number was zero before. The city’s proceeds from the land sale likely decreased as a result, though the difference may not be large as market rents in the vicinity can sometimes approach 120% of AMI. Like the Blocks 7 & 8 project, this one has been reconfigured to be taller and less bulky. The project will now have a 45 story portion and a 6 story portion, rather than two 26-story towers as before.
Other projects that were withdrawn or voted down at the post-election December 2025 JCRA meeting have obtained redevelopment agreements at the JCRA in recent months, including 310 Washington Street in October and 3000 Kennedy Blvd in July. Sources indicate that these were likely being held up by the Solomon administration as well.